Holberton Tulsa was my first project as Director of Operations. It was one of the most fulfilling professional project I had the opportunity to work on: taking a blank warehouse and transforming it to a magnificent school, where everything is automated and managed with the latest technologies.
Architecture
Visit of the initial location during Summer 2019 > Work on the layout with W Design > Produce the Revit project > Follow the on-site construction with Miller Tippens > Deliver the campus on time in January 2020.
IT & Infrastructure
After choosing the technologies and negotiating with suppliers, I went on-site for the setup of the network & infrastructure (Fortinet, Dell Servers, VMware ESXi, Crestron setup, NewTek TriCaster and so much more...!). Bellow picture of the hardware we configured with my co-worker and friend Alexandre Gautier. 
Stage Setup
From the drawing to the physical installation of a good stage setup (RAYZR & ROBE lighting fixture controlled via DMX by a Pharos Controller, LG TV wall feed through Crestron NVX, sound system powered by NEXO and Allen & Heath), still with my co-worker and friend Alexandre Gautier. 
Back to Top